Water Shutoff, Wed, 3/25/2026 – Water On

Posted on 03-24-2026

Update: Two main valves were replaced and the water is now back on. Thank you for your patience while this work was done. Wednesday, March 25, the Water Dept will shut off the water so a main valve at Condo 1 can be replaced. The work is expected to start sometime around 8 am and… Read more »

Mill Race Update 3/9/26, March Newsletter

Posted on 03-9-2026

Good News! Kinetics’ contractor was able to remove their equipment without having to dig up Mill Race Road. The March Newsletter is posted with signup sheets for the Easter Egg Hunt, Flower Basket Sale, Trout Derby and Cinco De Mayo party is posted in color on the website. We are also delivering the blank and… Read more »

Mill Race Repair and GVCA Fee Due Date Jan 15

Posted on 01-13-2026

First, there will be a contractor digging up a section of Mill Race Road near Village Club Drive tomorrow morning, Wednesday, January 13th, (or as soon as WEATHER PERMITS). Traffic will be using only one side of the road to pass. Please be patient and take turns in allowing usage in that area and be… Read more »

82 Bridge Closed/Detour

Posted on 10-14-2025

The Route 82 bridge will be closed in both directions starting October 14, 2025, for about one month. A crack has been located in one of the pillars. Check a live map for the best route to reach your destination. The simplest route to the other side of the bridge is shown below, taking Boyden… Read more »

Seeding

Posted on 07-12-2025

The parking lot will be closed early Monday morning 7/14/2025, for seeding of the new landscaping, but will reopen by 9 am, in time for the morning water aerobics class. Please do not walk or ride a bike through the seeded areas. The landscaping and seeding of the drainage trenches is scheduled for the week… Read more »

Parking Lot Closed Friday, July 11

Posted on 07-9-2025

Parking lot will close for landscaping Friday, July 11, 2025. PLEASE Do Not Walk on the seeded areas. The parking lot will re-open as soon as the seeding is complete, definitely in time for the Dive-in Movie Friday night. The landscaping will finish the parking lot by filling in and seeding the gaps behind all… Read more »

Construction Phase 6 – Parking Lot Opening

Posted on 06-20-2025

The Parking Lot’s final top-coat of pavement was put down Wednesday morning and the parking lines were painted Friday morning. All that is left is the landscaping. We will open the parking lot to light traffic today, Friday, June 20, at 3 pm. PLEASE, Do Not Park Trailers or Heavy Trucks on the new asphalt…. Read more »

Construction Phase 5

Posted on 06-15-2025

The parking lot will be closed Monday, 6/16/2025, for installation of the fabric layer and the final top coat of asphalt and will stay closed for several days to ensure the asphalt hardens enough to park on it without making depressions. Please Do Not Park on Village Club Road Monday or Tuesday between Village Parkway… Read more »

Construction Phase 4 – Updated

Posted on 06-2-2025

6/6/25 Update – The Parking Lot, Tennis Courts, and Outdoor Pool Entrance are Open. On Tuesday, the asphalt plant broke down as the contractor was close to finishing Phase 4, the base leveling coat. We opened the parking lot Wednesday but had to close it again Wednesday afternoon when asphalt plant was repaired and the… Read more »

Construction Phase 3

Posted on 05-19-2025

Phase 3 – The parking lot is closed for asphalt removal and base installation. The contractor has completed the new concrete curbs and drainage. The corroded conduit to the parking lot lights is being replaced, so there may be no lighting at night. Please use caution and do not enter the parking lot or construction… Read more »